Risk Register
Notice Kahua is a very flexible and customizable platform. In your domain, this application may have been modified to meet your company's needs. The online help uses default field labels for field names and describes standard workflows. Please check with your domain administrator for specific information about working in your organization's domain.
The Risk Register app allows you to track risk items for your project or program. Each risk item contains important dates, risk assessment and risk mitigation information. You can create one or more action items for a risk item. The action item is assigned to a user and explains the action that is needed to mitigate the risk using a task within Kahua. The action update from the task is then updated in the risk item record and then, if appropriate, the risk item can be closed.
Key elements of the Risk Register app are as follows:
-
You can track risk items for your project or program as they come up.
-
You can track the risk impact severity and probability. Based on your selections, schedule contingency and budget contingency values are calculated. These values can be manually overridden.
-
The numbers used to calculate contingency values based on risk assessments can be configured in the Configuration app > Applications tab > Risk Register > Additional Settings tab.
-
Action items related to the risk item can be tracked and assigned as tasks to Kahua contacts as the responsible party. These action items can be managed and closed when complete.
How to . . .
To create a new risk item, complete the following steps:
-
Review the header to ensure that you are in the correct project or partition.
-
Navigate to the application (Apps > Document Management > Risk Register).
-
To enter a new item, click New in the action bar. To modify an existing record, select it to open it in the detail panel and click Edit.
-
Complete the following fields as appropriate:
Note Depending on how this app is configured for your domain, there may be fields or sections listed here that do not appear for you, fields and sections that appear for you which are not listed here, or fields and sections which appear in a different order. If you have any questions, check with your domain administrator.
Field Description Details Number Allow Kahua to auto-number the record, or enter a different value.
Note The number format can be configured by your domain administrator. Refer to Number.
Date Reported By default today's date appears. Modify if appropriate. Title Enter a title for the risk item. Risk Description Enter a description of the risk item. Coordinator Select the person responsible for coordinating this risk item. Project Phase at Identification Make the appropriate selection.
Note This lookup list is managed in the Configuration app. Refer to Lookups.
Assessment Categories Impacted Select the appropriate impact categories. Click Select All to choose all of them.
Note This list is managed in the Additional Settings tab of the application Configuration. Refer to Additional Settings tab.
Impact Description Enter a description of the possible impact. Impact Severity Select an impact severity. Impact Probability Select an impact probability. Risk Rating The Risk Rating is calculated as the product of the selected Impact Severity and Impact Probability. Risk Importance This value is determined based on the Risk Rating.
Note This is configured in the Configuration app > Additional Settings tab > Risk Importance section. Refer to Additional Settings tab.
Potential Schedule Impact (in days) Enter the number of days of the possible schedule impact. Potential Budget Impact Enter the amount of the possible budget impact. Schedule Contingency Override Select this option to manually override the calculated Schedule Contingency value. Schedule Contingency This value is calculated based on the Risk Importance and Potential Schedule Impact values.
Note The numbers used for this calculation are configured in the Configuration app > Additional Settings tab. Refer to Additional Settings tab.
Budget Contingency Override Select this option to manually override the calculated Budget Contingency value. Budget Contingency This value is calculated based on the Risk Importance and Potential Budget Impact values.
Note The numbers used for this calculation are configured in the Configuration app > Additional Settingstab. Refer to Additional Settings tab.
Mitigation Risk Status Select the risk status.
Note This lookup list is managed in the Configuration app. Refer to Lookups.
Mitigation Plan Enter the mitigation plan. Timeline to Impact Select the appropriate range of days until impact.
Note This lookup list is managed in the Configuration app. Refer to Lookups.
Expected Date of Impact Enter the expected date of impact. Action Items Click Insert to insert a line in the Action Items grid. For more information on working with grids, refer to Item grids.
Subject Enter a subject for the action item. Responsible Person Select the Kahua contact responsible for providing an update for the action item. Date Assigned Date that the item is assigned to the Responsible Person. Due Date Enter a due date for the item. Complete Date The date the action item was marked complete appears here. Status The current status of the action item appears here. Action Needed Enter the action needed. Evaluation Date Closed Select the closed date when the item is closed. Resolution Select the resolution.
Note This lookup list is managed in the Configuration app. Refer to Lookups.
Resolution Notes Enter any notes for the resolution. Actual Schedule Impact Enter the actual schedule impact. Actual Budget Impact Enter the actual budget impact. Comments Enter any comments as appropriate. Comments from other users will appear here. References Upload or select any relevant files or documents. You can use drag and drop to add a file to this section. For more information on using this section, refer to References section.
-
Click Save when you are done.
Once a record is saved, the Risk Rating is calculated. The Risk Rating is calculated as the product of the selected Impact Severity and Impact Probability. Impact Severity and Impact Probability selections range from 1 (Very Low) to 5 (Very High).
Risk Rating = Impact Severity x Impact Probability
The Risk Rating value determines the Risk Importance. By default, the Risk Rating values are rated as follows:
-
Very Low - 1 to 3
-
Low - 4 to 5
-
Moderate - 6 to 12
-
High - 15 to 16
-
Very High - 20 to 25
Note These values are configured in the Configuration app > Additional Settings tab > Risk Importance section. Refer to Additional Settings tab.
The Risk Importance is used in the Schedule Contingency and Budget Contingency calculations. For more information, refer to Additional Settings tab.
To view the item risk ratings and risk importance for all items, select the Risk Register log view. For more information on log views, refer to Log Views and Log Reporting.
Once the risk register record is saved, action items on the risk register can be sent as tasks to the responsible party.
To send an action item as a task, complete the following tasks:
-
Ensure that you have saved the risk register item.
-
In the Action Items section, select Send Task.
-
The action item is sent as a task to the contact listed as the Responsible Person. For more information on working with tasks, refer to Tasks App.
-
If you need to remove the task from the selected Responsible Person after it has been assigned, select Recall. The task will be removed from their tasks app and you can assign it to another user or mark it as complete.
-
To see the response from the contact assigned the task, select the View Details icon
on the line item. -
When the responsible person marks the item as complete, the Status changes to Closed. The action item can be re-opened if necessary by selecting Re-Open. It can be returned to the original Responsible Person, or another contact can be selected in that field and the task can be sent to them.
If you have existing data that you want to import into this app, you can do so through the import process.
You will first generate an export of an existing record to access the correctly formatted spreadsheet file for the import. Once the exported file is available, add the appropriate values for the records you want to import to the exported spreadsheet. You can then import those records. For more detailed information on the importing process, refer to Importing records.
You can generate a report from a selected log view, or use one of the built-in reports available by default in each application. For more information on creating your own reports, including how to set up scheduled reports, refer to Creating ad hoc reports.
Note For information on modifying the logo that appears on reports in your project, refer to Managing report logos.
To generate a report from a log view with up to 10,000 records, click the More icon
and select Print. If your log view contains more than 10,000 records, the Print option will be disabled and you can select
to download the records to a CSV file instead.
To generate an application report, complete the following steps:
-
Navigate to the application.
-
Select Reports in the application title bar.
-
Select the report you want to run.
-
Apply any desired filters.
-
Select View or Download as appropriate. For more information, refer to Viewing Reports.
-
Click the Close icon
when you are done.
(print, send, view history, delete, etc.)
From the detail view of a record, there are several standard actions you can take. Depending on your permissions, some or all of the following options may be available to you:
-
View and View w/References - Select View or View w/References to open a PDF view of the current record. The PDF file can be printed or shared from the viewer by clicking on the Open PDF icon
.Note Only references where the Include on Send value is set to "Yes" are included in the View w/References.
Additionally, if Include Markup on Send is set to "Yes", any markups on the file are included. -
Discussions
- Select this icon to open the Discussions panel. If enabled in your domain, the discussions feature allows you to participate in public or private conversations associated with specific records. For more information, refer to Discussions. -
View History
- Select this icon to open the History page for the record. The history page provides details regarding all activity (creation, edits, saves, etc.) performed on the record. Click view edit to drill down into more detail on a specific action. Click hide edit to close the action detail. Click the Close icon
to close the history page. -
Send actions
- Click this icon to select an appropriate Send action for the record. The following options may be available to you:-
Copy Link and Copy Portable View Link - Select this option to copy a URL link for the record or record's portable view to your clipboard. This link can be sent outside of Kahua. Users with the appropriate permissions will be able to open Kahua directly to that record or portable view by using the link.
-
Copy QR Code and Copy Portable View QR Code - Select this option to generate a QR code for the currently open record or record's portable view. The QR code can be shared directly from your screen, or copied to your clipboard to be shared as appropriate. This QR code can be shared outside of Kahua. Users with the appropriate permissions will be able to open Kahua directly to that record or portable view by using the link.
-
Send - Select this option to open a new Kahua message with the open record included as an attachment. References with the Include on Send value set to "Yes" are also included. For more information, refer to Messages app.
-
-
Delete
- Select this option to delete the open record. You must agree to the confirmation message before the record is deleted.Alternatively, right-click on the record in the log view and select Delete, or select multiple records from the log view and select Delete.
Note If a record is deleted in error, your domain administrator may be able to recover it through the Recycle Bin app. For more information, refer to Using the Recycle Bin.
-
Open in a new window
- Select this option to open the current record as read-only in a new window (desktop host) or browser tab (web host). This allows you to navigate to other records in the original Kahua instance while keeping the read-only window or tab open for reference. To re-open the record on the read-only window or tab in Kahua, select Open in the header. -
Maximize
and Minimize
- Select Maximize
to open the record to a full screen view. From the full screen view, select Minimize
to return to the original view. -
Close
- Select the close icon
to close the currently open item.
Your domain administrator or another user with the appropriate permissions can configure the app in the Configuration application.
Important When working in the Configuration app, it is important to review the header and ensure that you are working at the correct level in the hierarchy, either the root domain or at a partition or project level.
Settings that you establish at the root domain or lower levels will inherit down the hierarchy until they are overridden. For more information on the hierarchical structure of Kahua, refer to Understanding the hierarchical structure of Kahua.
The Configuration app can be accessed directly through the apps list (Apps > Administration > Configuration), or, in some applications, by right-clicking on an application in the launch bar and selecting Configure. When you select Configure for an app from the launch bar, the detail view of the configuration page for that application opens automatically.
For general information on configuring this app in Configuration, refer to Application configuration.
The following items are specific to this application:
| Options | Description |
|---|---|
| Additional Settings tab | |
| Impact Probability Values |
Modify these values to change how the Schedule Contingency and Budget Contingency values are calculated, based on the calculated Risk Importance. Example If the Potential Budget Impact is $10,000, the Risk Importance is "Moderate", and the Impact Probability Moderate Value is set to .38 here, the Budget Contingency will be calculated as $3,800 ($10,000 x .38). |
| Risk Impact Categories |
Edit the Risk Impact Categories as desired. To remove a risk category, select it in the grid and click Delete. Note For more information on working with grids, refer to Item grids. |
| Risk Importance |
This section translates the calculated Risk Rating into a Impact Probability value. The Risk Rating is calculated as the product of the selected Impact Severity and Impact Probability. That numeric Rating Value is translated to an Importance level. The Importance level is used to determine the Impact Probability Value, which is used to calculate schedule and contingency values. Example By default, if the Risk Rating is calculated as 12, the Importance is Moderate. If the Importance is Moderate, then the Potential Budget Impact and Potential Schedule Impact are multiplied by the Impact Probability value of .38 to determine a Contingency amount. |
Application roles determine which actions users can perform in the app. Roles are assigned to groups in the Groups app > Permissions tab. Members of the group then have the permissions associated with the roles assigned to the group.
The following roles are available for this application:
| Role | Details |
|---|---|
| Administrator |
Full administration, including add, configure, create lists, edit, import, export, share, view, send, process, remove, and edit view templates. |
| Contributor |
Can add, edit, open, view, send, and process records. |
| LimitedView | This role works differently from other roles in that it does not grant access to any documents within an app. This is a restrictive role which will remove the following actions: Log, Quick Print, Send, Download, Export, Process, View PDF. |
| Moderator |
Can add, edit, import, export, remove, share, open, view, send, and process records. |
| Observer |
Can open, view, send, and process records. |
| Referencer |
View-only access to records. |
Note To manage these permissions, open the Groups app and assign the appropriate application role to the group. Only users with the appropriate permissions can manage application roles. For more information, refer to Managing Permissions.